**.A* 0 W UJ 0 UJ 0 Of n Welcome to the second Battalion Progress keport First, just a quick reminder of its purpose. it should be keeping us all, both Staffers and Drivers, swam of progress in all areas of the Project If you feel it is not doing so adequately, please feel free to pass your comments on to Paul Richmond at Windsor House. So far, the good news is that we are still on schedule. The Battalion worldwide communica- tion programme is now complete, except for a visit to B&W, now tabled for 61June. Generally, the programme has been well received. The majority of questions to have arisen concern strategy and clarity of direction. These are being addressed by Hilary in consultation with Bain & Co (see Tobacco Strategy, below). issue number 2. 261 may 1995 Project Battalion Windsor House, 50 Viro_ S,,,,-. L.ndo,, SW:F 01;L Telephone: 0171 222 79-9 Fax: 01-1 ZZ-1 4094 The next key date is the presentation to the CEC of the Diagnostic Report, scheduled for 12, June. PRODUCTION PROGRESS Key issues have been identified in each majorfunctional area anc de=ion mapping is in progress. The examples otclecisions under scrutiny include: Reorganisation of flue- cumd production in Chile; 'Product improvemeny development of Luciry SoIke in Indonesia; NEXTSTEPS Opportunity identification and priontisation is underway. with several meetings by the sub-4eams of leaf. R&D and production sched- led for late May- u . interim progress review and joint co-ordination meeting with Paul Adams (Marketing Driver). sched- uled for 1'- 2" June. EadKohrviorst productpon,oriiff MARKETING Kefth S. Duft Proiect Director Argentina. Brazil. Malaysia. Hong Kong/China and Switzerland. NEX7STEPS . Team to hold a working session on 31- May - I-June to generate findings. reach a consensus and agree options for improvements to decision making processes and organisation. . A meeting with Earl Kolinhorst rProduction' Driver). to be chaired by Keith Dunt. on 11 - 2- June. to cross-reference findings and agree forward action and team strudure. - Movement of Hc,16%ow export sourcing from Braa to Germany: and - Purchasing leverage of c3 garerte paper. - - Functionaibencnmarkingisin progress with Bain & Co's assist. ance. Companies being revie,~ include Pnilip Morris. Guiness. Pr=or & Gamble and Nestle. PROGRESS Interviews for the Diagnostic Phase have now been completed. , The exercise vivoKeed intemews b, Marketing Team members in the following locations: . - BAT (Germany). Brown & Williamson. SATCo (Staines). page (i) PWAdams marke&VDI~ff C) LEGAL -P. PROGRESS Lrl . The Legal Drive Team com. prises Stuart Chaffen. Tony Burke. Peter Clarke. Nelson Di?_ Joachim Dreyer and Neil Wdhington. co __J BAT Industries document for Province of British Columbia 3 November 1999 rssue number 2. 26~ mav 1995 A'kick-ofr meeting was held on 231 March with a folio. up meeting on 191 April. Co-ordination within the legal function is already well developed and discussions have focused on reviewing the eidstmg melliods of operation in the conted of Project Battalion. NEXTSTEPS Legal Drive Team to re-convene on 191 - 201 June. It will: - Consider the output from the Diagnostic Phase: - Agree upon benchmarking candidates and methodology; and - Establish a detailed work plan forthe Battalion Blueprint Phase. including the identification of cross-functional relationships and input into other Drive Team act.ities proposing the actions SAT would have to take to gain a leading position in each market Dy the year 2005. NEXTSTEPS The toba= strategy to be presented to the Group Soard on 61 June. Then to be dismmed at the joint riveting of the TSG. marketing directors. and regional directors on 141 June. as back- ground to their discussion of major brand strategies and prionfies. . At the same time. work with Bain & Co to ensure that the organisationall implicMions of the strategy are incorporated in the Battalion blueprint are to corin .nue. Hkvy Barton Pfarriing Staffer INFORMATION TECHNOLOGY Nei W217moon - Work is progressing as outlined in the last Progress ReporL TOBACCO STRATEGY PROGRESS In October 1994, the Group Board apprcied the objective of recapturing the number one position. The Team are currently, attend- ing an IT seminar by Professor I John Donovan of the Massacnu- I setts Institute of Technology in Boston, USA. Antonio Ame"C" ROt"gu0s f -, Ori~vv ' As part of the annual planning .ycle, in June the Group Board will review the tobacco strategy (i.e. how we are going to achieve the objective). In preparation. several meetings have bow held with the CEC to update the strategy from laist year. Srnral discussions have also been hold with Bain & Co who !re providing an ftemal'cha~enge to the strategy. CORPORATE AF.=AIRS PROGRESS Views an- being canvassed from Operating Groups on the following: The correct scope of the col"Porate affairs function for a truly international group: j - What are corporate affairs' target audiences: . Meanwhile. the Operating Organisation of the corpo- Groups have been preparing rate affairs function: and realistic. optimistic and pe_ssimisfic *scen2rios'torthe majortobacco NEXTSTEPS markets overthe ned decade. and : * The resulting analysm to shape part of the presentation to tlie CEC scheduled for 12, June. This will include: wpm P.7. ri) - Key areas that the corpo. rate affairs function Should tackle in an integrated tobacco group. and - The opportunities and challenges inherent in an integrated approach to corporate affairs. A6 QUWF`ndea- Corporalte Aflars Driver HUMAN RESOURCES PROGRESS * Each operating Group and Wndsor House have now re- 3 POnded to a diagnostic instrument designed to identify the key human resources issues. . e instrument focuses on two broad areas: - Management development and careeir and performance m2 nagement and Compensation. benefits and administration. ' Analysis of the data .91 be completed by 301 May. - The human resources key issue output will be available by 2"June. NECTSTEPS i- A meeting of the Human Re- sources Drive Team to be arranged in June. - Where needed. the Drive Team will utilise the human resources benchmark data already collected for a vainety of US and European multiLinationals. David'Stevens Hurnan Resources Drrder FINANCt PROGRESS A meeting of the Project Team was held an 151 - 161 May. cover- ing the following ground: - A basis and timetable for the mid-year update on 1995 brand/ Market results for the September TSG sub-group. Systems issues were resolved with IT involvement. C) CO c0 BAT Industries document for Province of British Columbia 3 November 1999 issue number 2. 26' mav 1995 work is under way on Member from each ooerating Produce an owrallsurn- accounts definitions. mainty in the Group and Windsor House is Mary to form a oasis for discussion area of sales and distribution. Team putting together a draft summary of at the FDs' meeting on 131 June. Members are to comment on the the status quo. issues. etc. in approach discussed at the meeting relation to their operations for DavidPwer by 311 May. discussion with the full rinance Accounting Statrer Team. - Agreement was reached NEXTSTEPS TAXATION on the aims for the Di2g nostic Phase. A work programme and * Project meeting SCIeduled for Work is progressinig as outlined timetable was agreed. 81 June to: in the last Progress Report. * Work has commenced on all - Discu, the above sum- Tom filikon the above. in particular, one Team maries of status quo, issues. etc Taxation Sraffer P.g. P-11 C) -r- U-I U, CC) .10 BAT Industries document for Province of British Columbia 3 November 1999